Electrical estimating with a wider perspective.

Clarity for renewable energy construction costs.

Connecting electrical scope with context to inform cost decisions before the build.

Renewable Energy System Estimation

Turn system requirements into installed scope.

Scope Connections

Following the power path from system equipment to the grid.

Each connection represents installed quantities and an interface that needs an owner.

How the estimate is built
Solar + Storage + AC-Coupled Single Line Diagram
DCLV ACMVHV
Conceptual solar and storage export pathA PV array exports through its inverter and MV transformer. The battery can both export and charge through its PCS, MV transformer, and the main transformer. The branches meet at MV collection, then connect through a circuit breaker, Gen-Tie, revenue metering, and the point of interconnection to the utility grid. Focus equipment for a brief explanation.Project SubstationPV ArrayDC generationPV InverterDC to ACMV TransformerLV to MVBatteryDC storageBattery PCSBidirectional conversionMV TransformerLV to MVMV CollectionMain TransformerMV to HVBreakerGen-TieRevenue MeterPOIUtility Grid

Why a unit rate is only a starting point

The same rating can require a different construction scope.

Pile refusal on one site. A longer gen-tie on another. A constrained substation at the point of interconnection. The estimate needs to explain those differences before the budgets can be compared.

Process

How the estimate is built and reviewed.

An estimating framework for owners, developers, and reviewers. Read the process from start to finish, or go straight to the system or cost driver you need.

Professional Profile

Construction, utility, and portfolio estimating.

Electrical construction estimating, utility-side interconnection experience, and utility-scale PV and storage estimating. Three perspectives on the same question: what does it take to build and connect the project?

Certified Professional Estimator · Project Management Professional

Profile Summary