Materials & Equipment
Motors, process equipment, lighting, HVAC, charging equipment, and auxiliary power loads establish the connected equipment list.
BESS Scenario Modeler
Project Net Present Value
Levelized Cost of Storage
Simple Payback
Initial CapEx
Annual Operating Cost
Delivered Energy
400 MWhChange power, duration, cost, operating assumptions or augmentation and review discounted cash flow, NPV, LCOS and payback on the same basis. The existing lifecycle and augmentation controls are included in preview access.
Review the Storage Estimating ProcessEstimate Stage Calc
Set each deliverable to None, Preliminary or Complete. Every requirement for a class must be met; a completed drawing cannot offset a missing investigation.
11 key deliverables in preview. Advanced access includes the complete technology-specific matrix.
The deliverable gates are an illustrative solar and storage adaptation. Complexity selects a position within the reference range for a class; it does not change the deliverable requirements.
AACE RP 18R-97 addresses process industries. Classification follows deliverable maturity, while project-specific accuracy requires risk analysis. See RP 18R-97 and AACE’s classification guide.
PV+Storage Sizer
Run the same PV array, POI limit and battery through AC and DC coupling. The model prioritizes clipped solar, then fills from available PV for evening discharge.
Annual Energy Delivered
Clipped Energy Recovered
Blended Cost of Energy
Year 1 Value vs. PV Alone
Dotted reference: POI limit. ¹Charge is shown as AC-equivalent source power.
AC storage can recover POI clipping. DC storage can also reach energy clipped at the inverter, subject to battery power and energy limits.
| Annual and Installed Measures | AC Coupled | DC Coupled |
|---|---|---|
| Energy Delivered | 257.2 GWh | 265.2 GWh |
| Clipping Recovered | 8.5 GWh | 14.2 GWh |
| Storage Conversion Losses | 8.8 GWh | 6.5 GWh |
| Installed Capital Cost | $206.8M | $204.0M |
| Blended Cost of Energy | $83.6/MWh | $80.1/MWh |
| Year 1 Energy & Capacity Value | $18.2M | $18.5M |
| Value Less Annualized Cost | −$2.4M/yr | −$1.8M/yr |
Unlock site and efficiency calibration, detailed cost and value inputs, representative-day selection and sizing curves.
Annual results weight 36 synthetic days: 12 months × clear, partly cloudy and overcast conditions, each at 15-minute resolution. The solar resource scales a generalized profile; no location-specific weather data is loaded. Daily storage operation returns to its initial state of charge.
The battery captures clipping first and can top up from PV before evening discharge. It does not charge from the grid or optimize prices. Cost of energy uses discounted capital, O&M and modeled delivery over the selected life, with PV degradation. Taxes, incentives, financing, battery replacement and augmentation are excluded here. Cost and value inputs are illustrative calibration assumptions from the supplied example.
For architecture context, see the NREL/NLR PV-plus-battery technology baseline. This tool does not reproduce that model or its cost data.
Interconnection Cost Study
Build a screening ROM for the project substation, Gen-Tie, utility POI and network upgrades. Study maturity changes the cost bands and the remaining schedule.
Likely Interconnection Cost
Cost per Plant Capacity
Likely Energization
Critical Path
Low · likely · high, $M. Network upgrades remain an allowance until utility scope is defined.
Accent bars: likely critical path. Pale extensions: high-case finish. Workstreams run in parallel after the study / agreement milestone.
| Transformer Rating Basis | 157.9 MVA at 0.95 power factor; 1 unit at ≤200 MVA each |
|---|---|
| MV Feeders | 5 feeders at 30 MW per feeder |
| Gen-Tie Basis | 3 mi · single circuit · flat terrain |
| Study Maturity | System Impact Study; facility band -20% / +30% |
| Transformer Supply | 130 weeks + 2 months to set; order 2 months after agreement |
| Network Upgrades | $50/kW likely allowance; utility-determined scope may differ |
| Escalation | 0% · constant screening dollars |
Unlock unit-rate and lead-time calibration, early transformer procurement, voltage-distance sensitivity and a copyable ROM summary.
Unit rates and phase factors are screening ballparks retained from the supplied example, not independently verified market benchmarks. Base rates: $1.7M/mi Gen-Tie and $24/kVA main transformer at 138 kV, before outlook and escalation factors.
The project substation includes transformer supply and a balance-of-substation allowance. POI scope includes a station arrangement factor and remote-end allowance. Network upgrades are a separate allowance, not a load-flow or utility facilities study. Route acquisitions, financing, tax and project-specific utility conditions are not modeled.
Schedule branches run in parallel after the study / agreement milestone. Energization follows the latest branch plus commissioning. Early ordering moves transformer procurement up to 12 months ahead of agreement and introduces commitment risk; it does not accelerate studies, site permitting or utility construction.
System Fundamentals
Declare the DC array rating and the ratio of DC capacity to AC inverter capacity to calculate the implied AC equipment rating.
AC Inverter Capacity Implied by This Ratio
8MWac
10 MWdc ÷ 1.25 = 8 MWac
This compares equipment ratings. The ratio is not an efficiency, an energy forecast, or a grid export limit.
Actual equipment comes in discrete sizes. Module and inverter selections, layout, and connection requirements determine the installed quantities.
System Fundamentals
An equipment schedule is only a starting point. Connections and installation conditions must be defined before applying assemblies or a cost basis.
Expand a topic to see typical equipment, installation roles, and scope interfaces.
Motors, process equipment, lighting, HVAC, charging equipment, and auxiliary power loads establish the connected equipment list.
The owner and equipment suppliers define operating needs; the electrical designer develops the load basis and the installer connects the equipment.
Distinguish equipment supply from its feeder, disconnect, control wiring, and final connection. Confirm which loads operate together.
Service and distribution voltage affect transformers, switchgear, cable insulation, terminations, and equipment compatibility.
The utility and electrical designer establish the voltage basis. Qualified installers and testing specialists work to the selected equipment requirements.
Identify the utility delivery voltage, project distribution voltage, and each transformation point. Keep utility-owned and project-owned equipment distinct.
Switchboards, transformers, breakers, inverters, and PCS units have capacity and duty ratings that drive equipment selection and counts.
Designers specify the required duty; manufacturers provide rated assemblies. Installation crews set and connect them, with rigging support where required.
Separate nominal capacity from installed equipment capacity and the permitted operating limit. Include accessories and connections outside the vendor package.
Radial or loop feeders, buses, duct banks, panels, and switching devices establish how power reaches each load or generation block.
The designer defines the arrangement. Electrical crews install the feeders and equipment; the owner or utility operates the completed system within its boundary.
Trace every feeder from source to destination. Identify spare ways, future provisions, temporary distribution, and interfaces with existing systems.
Breakers, fuses, relays, instrument transformers, and associated wiring support the protection scheme.
Protection engineers establish coordination and settings. Relay technicians and testing specialists verify the installed system with the owner and utility.
Confirm who provides studies, settings, devices, testing, and utility acceptance. A supplied breaker does not automatically include all protection work.
Controllers, PLC or RTU panels, EMS, SCADA interfaces, sensors, fiber, network equipment, and control power connect operational systems.
Controls integrators and equipment vendors configure the interfaces; electrical and communications crews install the physical connections. Operations staff use the completed controls.
Define hardware, communications, programming, licenses, telemetry, cybersecurity requirements, and integration testing separately.
Cable, conduit, trench, duct bank, pull structures, and restoration quantities depend on the installed route and transitions.
Survey and design teams establish routes; civil and electrical crews execute the excavation, pathway, and cable work with equipment operators.
Account for vertical rises, equipment approach, bends, crossings, and termination allowances. Identify who excavates, backfills, and restores each route.
Conduit, fittings, conductors, cable tray, splice kits, warning tape, and pull structures form complete installation assemblies.
Electrical crews assemble pathways, pull cable, and make connections; civil crews and operators support underground installation where included.
State direct burial versus raceway, installation method, circuit basis, and included fittings. Keep material supply and installation responsibility explicit.
Strut, brackets, hangers, tray supports, embedded items, anchors, and equipment foundations transfer installation loads to the structure or ground.
Structural and electrical designers coordinate the support basis. Concrete, steel, and electrical crews install their respective portions.
Identify structural design, embeds, foundations, supports, seismic provisions where applicable, and field attachment responsibility.
Ground grids, bare conductors, rods, connectors, bonding jumpers, test points, and equipment bonds make up the installed grounding system.
The designer defines the grounding basis. Electrical crews install and bond the system; qualified testing specialists verify the specified performance.
Separate the site grid, equipment bonds, lightning-related scope, and testing. Coordinate vendor, building, and utility interfaces.
Lugs, glands, stress-control kits, separable connectors, splice components, labels, and enclosure entries complete the ends of cable runs.
Electrical crews and qualified cable jointers prepare connections; testing specialists verify the completed circuits as specified.
Count both ends, splices, and equipment interfaces. Confirm connector compatibility, vendor-supplied kits, specialty labor, and associated testing.
Temporary roads, mats, laydown, lifting equipment, delivery staging, and equipment transport may be needed before installation can start.
Construction management coordinates logistics with civil crews, delivery teams, riggers, and equipment operators.
Assign road preparation, unloading, storage, final placement, access maintenance, and restoration. Confirm delivery and lifting limits.
Lifts, scaffolds, fall-protection provisions, elevated supports, and material handling equipment change the installation method.
Installation crews use the required access equipment; trained operators and site supervision coordinate its use and availability.
Identify who furnishes access equipment, setup and relocation time, shared use, and restrictions around other work.
Rock excavation, dewatering, unsuitable soils, corrosion protection, stabilization, weather protection, and restoration can add scope.
Geotechnical and design teams establish the basis. Civil crews, operators, and specialty subcontractors address the defined conditions.
Record assumed ground conditions, investigation coverage, exclusions, allowances, and responsibility for changed conditions.
Temporary distribution, bypass equipment, replacement components, and shutdown support may be required to complete an interface.
The owner or utility controls the operating window. Authorized operations staff, qualified electrical crews, and testing teams coordinate the planned work.
Define the permitted window, temporary service, switching responsibility, advance approvals, and return-to-service acceptance.
Temporary feeds, staged deliveries, partial systems, repeated mobilizations, and protection of completed work affect the scope.
Project controls, construction management, trade foremen, and owner representatives coordinate the sequence and handoffs.
Distinguish one continuous installation from multiple phases. Identify temporary work, remobilization, partial turnover, and trade interfaces.
Test equipment, temporary power, instrumentation, consumables, and documentation support specified verification and commissioning.
Testing specialists, relay technicians, vendors, and commissioning teams perform the defined checks; the owner or utility may witness acceptance.
Identify factory versus field tests, pre-energization work, integration and performance tests, witnessing, retesting, and included vendor support.
Labels, record drawings, operating manuals, spare parts, training materials, and closeout records complete the handover package.
The contractor, designers, vendors, and commissioning team assemble deliverables. Owner operations and maintenance staff receive the completed system.
Define documentation, training, spares, warranty start, punch-list completion, and the point when operational responsibility transfers.
These examples identify work packages and interfaces. Project drawings, specifications, supplier scope, and execution plans establish the actual quantities and responsibilities.
Professional Access
Free access only previews a limited basis of core scenario calculations and model inputs. Unlock access for extended controls below.
Full technology-specific matrix of up to 22 deliverables, a target class, contingency comparison and an exportable gap report.
Site resource, efficiencies, capital and operating cost calibration, energy values, representative-day selection and storage sizing curves.
Unit rates, terrain and labor factors, lead times, at-risk transformer procurement, a voltage-distance matrix and an exportable ROM summary.